Nortech Marine needed to move a 33-tonne press brake from Ross-on-Wye to its fabrication workshop in Lerwick. The weight of the machine and its overall height once loaded were the main constraints. LTS needed to plan a route that could accommodate both on the road to Aberdeen Docks and on the final leg from Lerwick’s ferry terminal to the workshop yard.
LTS planned the journey in three stages. The first was the road movement from Ross-on-Wye to Aberdeen Docks, followed by the ferry crossing to Shetland and the final delivery leg to Nortech Marine’s yard. The team used a specialist heavy-haul unit and trailer operating under STGO Category 2.
LTS coordinated the movement orders, ferry bookings and crane arrangements. The team also prepared the lift plans, risk assessments and method statements for the job.
LTS successfully delivered the 33-tonne press brake to Nortech Marine’s yard in Lerwick.