Pelagia needed to relocate a storage tank from its Bressay site to Greenock. Once on the trailer, the load measured 4.9 m high and 4.1 m wide. That put it just 100 mm below the 5 m ferry height limit. LTS also had to check bridge clearances, plan the approach through narrow streets in Greenock and schedule the move within the permitted road travel window of 09:30 to 15:30.

The team visited the Bressay site to measure the tank and discuss the transport options with Pelagia. LTS’s Appointed Person designed the lift and prepared the lift plan, risk assessments and method statements. A crane supervisor oversaw the lifting operation, and LTS supplied the crane, mobile elevating work platform, trailer and crew. The team also booked the ferries, arranged the escorts and secured the wide-load movement orders.

High winds disrupted the ferries and pushed the planned road move back by a day. LTS submitted a revised movement order to the police, moved the transport to 22 November and delivered the tank safely to Pelagia’s Greenock site.

© 2026 LTS Shetland Ltd | Website by rw.digital